Melrose DesignsThe Complete Process: From Planning Permission to Building Regulations to Construction (2025 UK Guide)

 

By Kieran Atherton — Architectural Designer & Director of Melrose Designs

planning permission to building regulations process


Why This Guide Matters

Most homeowners (and many designers) underestimate how long and detailed the journey is from a first idea to a finished extension. They often ask:

  • “Do I need planning permission, or can I skip straight to drawings?”
  • “When do I need structural calculations?”
  • “What happens after Building Regulations approval?”
  • “Who informs Building Control and the builder?”

As someone who submits hundreds of planning and Building Regulations drawings every year across Wigan, St Helens & Greater Manchester, I built this guide to simplify the entire process.

planning permission to building regulations process

 

Sub-Topic Pages:

    1. Planning Permission Explained (Step-by-Step Checklist)

    1. Building Regulations Guide for Home Extensions

“The Melrose Method™ – A Clear Path from Planning to Construction”

planning permission to building regulations process


 

    1. Overview of the Full Journey: Planning → Building Regs → Construction

Here is the full process in a simple flow:

  1. Concept Design & Feasibility
  2. Planning Permission (if required)
  3. Technical Drawings for Building Regulations
  4. Structural Calculations
  5. Builder Pricing & Tendering
  6. Building Control Approval
  7. Construction Phase
  8. Sign-Off & Completion Certificate

Many clients don’t realise these are distinct stages, each requiring different types of drawings and paperwork.

The Melrose Method™ makes the journey predictable by breaking each stage into clear milestones.


 

    1. Planning Permission Stage (Optional, but often required)

When Planning Permission IS required

  • Side extensions creating wrap-arounds
  • Extensions near highways
  • Flats & HMOs
  • Major alterations to roof shape (in restricted areas)
  • New dwellings or conversions

Typical Planning Timeline

Stage                                Duration

Initial drawings               1–2 weeks
Submission                      Same day
Validation                        1 week
Consultation period      21 days
Decision                           8 weeks

What Melrose Designs supplies at this stage

  • Existing + proposed plans
  • Elevations + roof plans
  • Site plan with red/blue line boundary
  • Planning statements (when needed)
  • Location plans
  • Neighbour consultation advice

Designer Tips for Faster Approvals

  • Keep rooflines simple
  • Pre-check neighbour windows (avoid overshadowing issues)
  • Speak to neighbours before submission
  • Provide a clear design and access statement


 

    1. Building Regulations Stage (Always Required)

Planning permission only gives you permission to build, not approval how to build.

Building Regulations drawings contain:

  • Insulation specifications
  • Fire safety details
  • Structure and foundations
  • Drainage layout
  • Roof build-ups
  • Steel beams, joists & connection details
  • Ventilation strategy
  • Thermal calculations (SAP, U-values)

What Melrose Designs Provides

  • Full Building Control drawing pack
  • Structural calculations (working with engineers when required)
  • Detailed construction notes
  • Specifications for materials

Common Mistakes Homeowners Make

  • Thinking planning drawings = building regs drawings (they don’t)
  • Choosing a builder before getting regulated drawings
  • Starting work before Building Control approval


 

    1. Structural Calculations & Engineering

Once the architectural drawings are ready, a structural engineer calculates:

  • Steel beams (RSJs)
  • Padstones
  • Roof loads
  • Floor strengthening
  • Removal of internal walls
  • Foundations and ground-bearing checks

Designer Tip:

Always design the steel layout early.
A redesign at construction stage is expensive and delays the build.


 

    1. Builder Pricing, Tendering & Contracts

Once Building Regulations drawings + structural calculations are complete:

You can now:

  • Get quotes from multiple builders
  • Compare prices based on the same information
  • Avoid “guess quotes” that lead to variations later

Tip for Homeowners

  • Ask for a fixed-price schedule with:
  • Start and finish date
  • Payment stages
  • List of included & excluded items


 

    1. Building Control Approval

Two options:

  • Private inspector (Approved Inspector)
  • Local authority Building Control

Both will:

  1. Check the drawings
  2. Inspect key stages of the build
  3. Issue a Completion Certificate

Stages Building Control Usually Inspects

  • Foundations
  • DPM / concrete pour
  • Structural steel installation
  • Insulation before plasterboard
  • Final completion


 

    1. Construction Phase Timeline

Every build differs, but here is a typical extension timeline:

Stage                                                       Duration (Approx.)

Groundworks & foundations              1–3 weeks
Drainage                                                 1 week
Block/brick walls                                  2–4 weeks
Roofing                                                    1–2 weeks
Windows & doors                                  1 week
First fix (electrics/plumbing)             1–2 weeks
Insulation & plasterboard                   1–2 weeks
Plastering                                               1 week
Second fix                                               1–2 weeks
Snags & completion                              1 week

Total typical duration: 8–16 weeks depending on size.


 

    1. The Melrose Designs Difference (E-E-A-T)

Why homeowners choose Melrose Designs

  • 10+ years specialising in home extensions
  • 1,000+ successful planning & Building Regs submissions
  • Background in structural & BIM coordination
  • Fast lead times (planning drawings in 7–14 days)
  • Clear communication with councils, engineers & builders

A refined process known as:

“The Melrose Method™ – A Clear Path from Planning to Construction”


 

    1. FAQs 

How long does planning permission take in the UK?

Typically 8 weeks after validation.

Do I need Building Regulations approval?

Yes — almost every extension requires Building Regulations even if planning isn’t needed.

When do I need structural calculations?

Anytime a beam, opening, or load-bearing wall is involved.

Can builders start work without Building Control approval?

No — this risks enforcement action and invalidates certification when selling the property.


 

  1. Quick-reference Table

Understanding the Planning Permission to Building Regulations Process

Stage

Purpose

Required?

Who Does it?

Planning Permission

Permission to build

Sometimes

Melrose Designs

Building Regulations

Ensures safe construction

Always

Melrose Designs

Structural Engineering

Beam & load design

Usually

Engineer

Builder Tendering

Accurate pricing

Always

Homeowner